More gallery projects to come...
Expanded project list:
Higher Education
Center for Health Sciences South Tower Seismic Renovation
UCLA, 2011-2013, $210M (total project cost)
Seismic retrofit of 443,000 SF former teaching hospital. Phased construction converted in to high-rise flexible research labs. Extremely challenging and congested site in occupied building. Core and shell achieved LEED platinum.
ZGF Architects | PCL Construction
Elkins Auditorium expansion / classroom annex / academic center
Pepperdine University, 2008, $20M
Subterranean tiered classroom building, expansion/upgrade of teaching auditorium and renovation of 40,000 SF academic and lab building In the central campus. NTD Architects
HOK Architects | Millie & Severson
Keck Science Center Renovation
Pepperdine University, 2008, $2M
New chemistry, biology, and natural science lab and classroom renovation. GMax contract, occupied building.
NTD Architects | Millie & Severson
Broadcast Studio
Pepperdine University, 2006, $250K
Live network uplink Interview facility. On campus TV studio for live interviews of faculty experts and distinguished community members. Full studio (sound attenuated) construction in occupied building during school year.
Studio Bauton | Environmental Contracting
Smothers Theatre and Arts Plaza
Pepperdine University, 2004, $1.5M
Lobby, plaza and stage lift renovation. Upgrade and expansion of restrooms, lobby, box office, entry terrace, and Gala orchestra pit lifts. Night sky modeled In LEDs penetrating Newmat sound attenuating waveform ceiling. Exterior art & sculpture plaza with new water features, specimen palms, hand-painted Malibu tile, stone cladding, concrete furniture, and landscape lighting. ASLA Merit Award 2005
NTD Architects / EPT (landscape) |Environmental Contracting
Rockwell Academic Center
Pepperdine University, 2000, $1M
20,000 SF lab / office remodel. Faculty offices, sports medicine and animal labs, special equipment, renovation performed during academic year.
NTD Architects | Turner Construction
K-12
Creativity and Technology Center
The Thacher School, 2019-2021, $22M
Directed entitlements, design and construction of $68M capital program. Construction of two new buildings and multiple surge spaces. ENR Best Project 2021
Blackbird Architects | PENTA Building Group
Dining Hall
The Thacher School 2017-2019, $13M
Mitigations and monitoring, design and construction of new dining hall and commercial kitchen for private boarding school. Extensive landscape improvements providing outdoor entertainment and dining as well as extensive accessibility improvements. Opened in time for 2019 academic year.
Blackbird Architects | PENTA Building Group
Rancho Campana High School
Oxnard Union High School District 2014-2016, $61M
New high school - design, construction, entitlements & permitting. CHPS project. CMAA Project Achievement, CASH/AIACC Henry S. Greene Design +Planning award 2017
HMC Architects / SC Anderson (contractor)
Adolfo Camarillo and Hueneme High Schools Aquatics Centers
Oxnard Union High School District 2013-2014, $3.6M
Two new pools and pool buildings on existing occupied campuses. Bundled project performed under a single construction contract. LLB delivered on time and under budget. CMAA Project Achievement Award 2015
Blackbird Architects / Arch Pac | SC Anderson (contractor)
Juanita Tate Academy
Los Angeles Unified School District 2009-2011 $25M
New elementary school on constrained mitigated brownfield site. Subterranean parking, FIFA soccer field.
Dougherty & Dougherty | Suffolk Construction
Olympic High School
Santa Monica / Malibu School District, 2017, $
Modernization of continuation high school Multiple phased renovation
NAC Architecture
South Gate High School
Los Angeles Unified School District, 1999, $2.7M
Safety & Technology upgrade.Bond BB Owner's rep for computer, security, PA, and fire alarm upgrade across entire campus. Year-round school schedule.
Gage Middle School Huntington Park
Los Angeles Unified School District, 1999, $1.2M
Safety & Technology upgrade. Year-round campus.
Utilities / Infrastructure
Wastewater Flow Equalization Station
Pepperdine University 2000-2001, $2M
Subterranean wastewater lift station (below campus parking lot). Progressive cavity pumps, air system, Johnson Controls and Automated Logic Control PLC. Stand-by generator and full redundancy of major systems. Sound attenuation. Commissioning, contingency documentation, and staff training.
Civiltec Engineering | Schuler Engineering (contractor)
Force main upgrade (Malibu Canyon Rd.)
Pepperdine University 2003
Replacement of air release valves on 4-mile force main and reclaimed water pipelines in Malibu Canyon Road. Required traffic diversion. Interfaced with city of Malibu, LA County Public Works, and Tapia Municipal wastewater facility.
Civiltec Engineering | Ferry Construction
Commercial
Malibu Pavilion
Malibu, CA, 1990-1991, $3M
Trophy commercial building. Subterranean parking, view suites and terraces. Redwood siding, curved standing seam metal roof, skylight.
Ed Niles, FAIA | Sequoia General Contractor
Custom residential
Private Residence
Malibu, CA 1991-1995, $2.7M
Ultra modern residence on 17 acre ocean view site. 250,000 lb structural steel frame, radius stainless interior and exterior panels, curved glass and wall finishes, outbuilding, sauna, weight room, helipad. Featured extensively in print and film. Published in Global Architecture (GA)
Ed Niles, FAIA | Sequoia General Contractor
Private Residence
Brentwood 1994-96, $3M
Ultra modern residence. Demolition of existing residence. Construction of new steel frame and glass structure. Radius aluminum panels, glass, steel, stone, Japanese roof garden, horizon pool, solarium. Published in Global Architecture (GA), Architectural Digest
Ed Niles, FAIA | Sequoia General Contractor